Enforcement Rules of the Nuclear Materials and Radioactive Waste Management Act Article 20

The decommissioning plan prepared by the operator under Paragraph 1, Article 14 of this Act shall include the following contents:1.Facility overview.2.Decommissioning objectives and time schedule.3.Decontamination methods and radioactive waste reduction measures.4.Class, characteristics, quantity, treatment, transportation and storage of radioactive waste.5.Radiation dose evaluation and radiation protection measures.6.Environmental radiation monitoring.7.Personnel training.8.Material and accounting records management of nuclear source material or nuclear fuel.9.Reutilization plan of factory building or land.10.Quality assurance program.11.Accident response scheme.12.Other matters designated by the competent authority.The decommissioning plan prepared by the operator under Paragraph 1 of Article 23 of this Act shall include the contents as listed in the above Subparagraphs 1~7 and 9~11 as well as other matters designated by the competent authority.
中文原文 放射性物料管理法施行細則第20條
經營者依本法第十四條第一項規定擬訂之除役計畫,應載明下列事項:
一、設施綜合概述。
二、除役目標及工作時程。
三、除污方式及放射性廢棄物減量措施。
四、除役廢棄物之類別、特性、數量、處理、運送及貯存。
五、輻射劑量評估及輻射防護措施。
六、環境輻射監測。
七、人員訓練。
八、核子原料或核子燃料料帳管理。
九、廠房或土地再利用規劃。
十、品質保證方案。
十一、意外事件應變方案。
十二、其他經主管機關指定之事項。
經營者依本法第二十三條第一項規定擬訂之除役計畫,應載明前項第一款至第七款、第九款至第十一款及其他經主管機關指定之事項。

English translation for reference only; the Chinese text prevails. Not legal advice.