Enforcement Rules of the Nuclear Materials and Radioactive Waste Management Act Article 19-1

Within six months of completing the decommissioning plan according to Paragraph 1 of Article 14 or Paragraph 1, Article 23 of this Act, the regulation of decommissioning shall be lifted after the operator submit the report of completion of decommissioning to the competent authority for inspections and approval.After the site of the facility is decommissioned according to the first paragraph, the annual individual effective dose to general public shall not exceed 0.25mSv.The report of completion of decommissioning referred to Paragraph 1 shall include the following contents:1.Decommissioning strategy and related implementation of the facilities.2.Radiation protection for the workers and the public during the decommissioning process.3.Results of the radiation dose survey at the final site.4.The management of radioactive waste.5.Subsequent management of the post-decommissioning site.6.Other items designated by the competent authority.
中文原文 放射性物料管理法施行細則第19-1條
經營者應於依本法第十四條第一項或第二十三條第一項規定實施除役計畫完成後六個月內,檢附除役完成報告,報請主管機關檢查並核准後,解除除役管制。
依前項規定除役後之設施場址,其對一般人造成之個人年有效劑量,不得超過○.二五毫西弗。
第一項除役完成報告,其內容應包括下列事項:
一、除役策略及作業情形。
二、除役作業人員及民眾之輻射防護。
三、最終場址輻射劑量調查結果。
四、放射性廢棄物管理作業。
五、除役後場址後續管理作業。
六、其他主管機關指定之事項。

English translation for reference only; the Chinese text prevails. Not legal advice.