Enforcement Rules of the Implementation of Nuclear Reactor Facilities Regulation Act Article 6

Pursuant to Article 9 of this Act, after nuclear reactor facility has been formally operated, the licensee shall submit respectively, prior to a six -month period before the expiry of every decennium, to the competent authority for review and approval the integrated safety analysis report containing following items:1. The backtracking and the review of operation of the facility: including the backtracking and the evaluation of the operation safety, the radiation safety and the management of radioactive waste.2. The review of items to-be-corrected or to-be-upgraded on the facility: including the review of issues related to items to-be-corrected or to-be-upgraded, the committed corrective actions or the explanations on items for upgrading.3. Overview: giving a peroration for the forthcoming decennium of operation period, based upon items provided under the preceding two subparagraphs, about items to be heeded, committed corrective actions and the schedule.4. Other items designated by the competent authority.
中文原文 核子反應器設施管制法施行細則第6條
經營者應依本法第九條規定,於核子反應器設施正式運轉後,每屆滿十年之六個月前,檢具包括下列事項之整體安全評估報告,報請主管機關審核:
一、設施營運狀況之回顧及檢討:含運轉安全、輻射安全及放射性廢棄物營運之回顧與評估。
二、設施待執行之改善或補強事項檢討:含機組待改善或補強問題檢討、承諾改善或補強事項說明。
三、總結:根據前二款事項,總結下一個十年運轉周期中應注意之事項、改善承諾及時程。
四、其他經主管機關指定之事項。

English translation for reference only; the Chinese text prevails. Not legal advice.