Enforcement Rules of the Nuclear Materials and Radioactive Waste Management Act Article 8

Before to apply for operating license of nuclear source material or nuclear fuel production or storage facility according to Paragraph 1 of Article 9 of this Act, the applicant shall submit a trial operation plan to the competent authority after completion of construction of the production or storage facility to apply for trial operation at first.After trial operation is finished in accordance with the above paragraph, a letter of application enclosed with the following documents shall be submitted to the competent authority to apply for operation license:1.Safety analysis report of the latest edition.2.Technical specifications of the facility operation.3.Trial operation report.4.Incident response plan.5.Photocopy of the storage permit(s) or entrusted treatment contract(s) issued by domestic and/or foreign radioactive waste final disposal facility.6.Other documents designated by the competent authority.The competent authority shall finish examination of the above-mentioned application within 3 months.
中文原文 放射性物料管理法施行細則第8條
依本法第九條第一項規定申請核子原料、核子燃料生產或貯存設施運轉執照者,應於生產或貯存設施興建完成後,先檢附試運轉計畫,向主管機關申請核准進行試運轉。
依前項規定進行試運轉完成後,應填具申請書,並檢附下列資料,向主管機關申請核發運轉執照:
一、最新版之安全分析報告。
二、設施運轉技術規範。
三、試運轉報告。
四、意外事件應變計畫。
五、國內、外放射性廢棄物最終處置設施之貯存許可或代處理契約影本。
六、其他經主管機關指定之資料。
主管機關對於前項申請案之審查,其處理期間為三個月。

English translation for reference only; the Chinese text prevails. Not legal advice.