Soil and Groundwater Pollution Remediation Act Enforcement Rules Article 14

The content of a soil and groundwater pollution control plan (herein referred to as a pollution control plan) proposed pursuant to Article 13, Paragraph 1 or Article 24, Paragraphs 3 and 7 of this Act should include the following items:1. Information concerning plan submitter, writer, and implementer.2. Plan outline.3. Basic information concerning site.4. Current status of site and pollution situation.5. Pollution investigation method.6. Pollutants, scope of pollution, and severity of pollution.7. Pollution control objective and method. If soil is to be handled off-site, the control plan must include off-site soil handling method, facilities, and control measures.8. Pollution monitoring method.9. Disposal or pollution control.10. Site health and safety management.11. Control results self-verification method and sampling and testing plan.12. Plan implementation schedule.13. Estimated funding.14. Other matters specified by the competent authority.When the information in the first subparagraph of the foregoing paragraph is submitted by a juridical person, information concerning the juridical person, its statutory responsible person, and the case manager must be included.The control results self-verification method and sampling and testing plan in Paragraph 1, Subparagraph 11 must include a representative soil and groundwater sample sampling method.
中文原文 土壤及地下水污染整治法施行細則第14條
依本法第十三條第一項、第二十四條第三項及第七項規定提出之土壤、地下水污染控制計畫(以下簡稱污染控制計畫),其內容應包括下列事項:
一、計畫提出者、撰寫者及執行者資料。
二、計畫大綱。
三、場址基本資料。
四、場址現況及污染情形。
五、污染調查方式。
六、污染物、污染範圍及污染程度。
七、污染控制目標及方法。
如採行土壤離場處理者,應包含土壤離場之處理方式與設施及管制措施等。
八、污染監測方式。
九、清理或污染防治。
十、場址安全衛生管理。
十一、控制結果之自行驗證方式及採樣檢測規劃。
十二、計畫執行期程。
十三、經費預估。
十四、其他主管機關指定之事項。
前項第一款之資料,由法人提出者,應包括法人、負責人及專案經理人之資料。
第一項第十一款控制結果之自行驗證方式及採樣檢測規劃,應包括具代表性之土壤、地下水樣品採樣方法。

English translation for reference only; the Chinese text prevails. Not legal advice.