Renewable Energy Development Act Article 8

When an operator of renewable energy power generation equipment requests for connection to the power grid, the electricity transmission and distribution enterprise shall collaborate with the operator under Articles 8 and 18 of the Electricity Act. The technical regulations on parallel connection to the power grid shall be drafted by electricity transmission and distribution enterprises and shall be submitted to the central competent authority for approval.In the case of a grid connection in accordance with the preceding paragraph, the associated costs of strengthening the power grid beyond the existing networks may be shared between the electricity transmission and distribution enterprises, and the cost-sharing mechanism shall be drafted by the electricity transmission and distribution enterprises and submitted to the central competent authority for approval. If necessary, the central competent authority may invite relevant government agencies, scholars, experts, and organisations to form a committee to review the cost-sharing mechanism.When the installed capacity of renewable-energy-based electricity generating enterprises and the installed self-use renewable energy power generation equipment is less than 2,000 kilowatts, the installers may independently or jointly set up transformer equipment, install networks, and connect to the power grid. The rights and obligations of jointly setting up the equipment shall be decided through negotiation between the installers. In case of any disputes, the regulations prescribed in Article 19 shall apply mutatis mutandis.The installer of the renewable energy power generation equipment shall install and maintain the circuits connecting the renewable energy power generation equipment and power grid. If necessary, the electricity transmission and distribution enterprises with which the power generation equipment is interconnected shall provide necessary assistance; the installers of the renewable energy power generation equipment shall bear the costs incurred.
中文原文 再生能源發展條例第8條
再生能源發電設備設置者要求與電力網互聯時,輸配電業應依電業法第八條及第十八條規定辦理;其併網技術規範,由輸配電業擬訂,報請中央主管機關核定。
依前項規定互聯時,在既有線路外,加強電力網之成本,得由輸配電業及再生能源發電設備設置者分攤;其分攤方式,由輸配電業擬訂,報請中央主管機關核定,必要時,中央主管機關得邀集相關部會、專家學者、團體組成審議會,審定成本分攤方式。
再生能源發電業與設置利用再生能源之自用發電設備未達二千瓩者,得單獨或共同設置變電站、引接線路與電力網互聯;其共同設置之相關權利義務,應由設置者協議之,如有爭議,準用第十九條規定辦理。
再生能源發電設備及電力網連接之線路,由再生能源發電設備設置者自行興建及維護;必要時,與其發電設備併網之輸配電業應提供必要之協助;所需費用,由再生能源發電設備設置者負擔。

English translation for reference only; the Chinese text prevails. Not legal advice.