Regulations for the Management of Setting up Renewable Energy Power Generation Equipment of Power Users above a Certain Contract Capacity Article 11
The central competent authority may send personnel to inspect the compulsory user of renewable energy, and the user shall provide relevant documents or necessary assistance, and shall not evade, impede or refuse. If the compulsory user of renewable energy evades, impedes or refuses the inspection, the central competent authority may exclude the capacity of the corresponding equipment in the performance results of the compulsory installed capacity.The central competent authority shall notify the compulsory user of renewable energy in writing before carrying out the inspection. If necessary, the central competent authority shall invite representatives of relevant agencies (institutions), scholars and experts to jointly carry out the inspection.
中文原文 一定契約容量以上之電力用戶應設置再生能源發電設備管理辦法第11條
中央主管機關得派員對再生能源義務用戶進行查核,再生能源義務用戶並應提供相關文件或必要之協助,不得規避、妨礙或拒絕。
再生能源義務用戶如有規避、妨礙或拒絕之情事者,中央主管機關就該設備容量,得不計入義務裝置容量之履行成果。
中央主管機關於執行查核業務前,應以書面方式通知再生能源義務用戶;必要時得邀集有關機關(構)代表、學者及專家偕同辦理。
再生能源義務用戶如有規避、妨礙或拒絕之情事者,中央主管機關就該設備容量,得不計入義務裝置容量之履行成果。
中央主管機關於執行查核業務前,應以書面方式通知再生能源義務用戶;必要時得邀集有關機關(構)代表、學者及專家偕同辦理。