Regulations for the Management of Setting up Renewable Energy Power Generation Equipment of Power Users above a Certain Contract Capacity Article 10
If the compulsory user of renewable energy fails to maintain the performed compulsory installed capacity, the central competent authority shall notify the compulsory user of renewable energy to make improvements within a time limit or pay the monetary substitution based on the unperformed compulsory installed capacity.If the average power generated (discharged) during the operation of renewable energy power generation equipment or energy storage facility installed by the compulsory user of renewable energy fails to reach 80%, and has not been improved within the time limit notified by the central competent authority, the performance results of the compulsory installed capacity shall not be included.
中文原文 一定契約容量以上之電力用戶應設置再生能源發電設備管理辦法第10條
再生能源義務用戶未維持已履行之義務裝置容量者,中央主管機關應通知再生能源義務用戶限期改善或按其未履行之義務裝置容量繳納代金。
再生能源義務用戶已設置之再生能源發電設備或設置儲能設備,於設備運轉期間之發(放)電功率平均值未達百分之八十,且未於中央主管機關通知期限內改善者,不得計入義務裝置容量之履行成果。
再生能源義務用戶已設置之再生能源發電設備或設置儲能設備,於設備運轉期間之發(放)電功率平均值未達百分之八十,且未於中央主管機關通知期限內改善者,不得計入義務裝置容量之履行成果。