Regulations on Governing the Establishment Approval for Reclaimed Water Operators and the Approval for Reclaimed Water Development Project Article 10
If the Reclaimed Water Operator needs to extend the construction period, it shall, within six months before the expiration of the construction schedule, attach the following materials and apply to the Competent Authority:1.Basic information: Name, responsible person, address, and contact information.2.Photocopies of the Reclaimed Water Development Project construction permit and wastewater (sewage) or effluent water use permit.3.Reasons and impact of the extension.4.Extended construction period.Extensions in the preceding Paragraph shall be limited to a maximum of two times; the total extended construction period shall not exceed half of the originally permitted construction period. This shall not apply to the cause not attributable to the Reclaimed Water Operator that have approved by the Competent Authority.For Reclaimed Water Development Projects initiated according to the Act for Promotion of Private Participation in Infrastructure Projects, this Article shall not apply.
中文原文 再生水經營業籌設許可及再生水開發案興辦許可辦法第10條
再生水經營業如需展延工期,應於施工期程屆滿前六個月,檢附下列資料,向該管主管機關提出申請:
一、基本資料:名稱、負責人、地址、聯絡方式。
二、再生水開發案興建許可及廢(污)水或放流水使用許可影本。
三、展延原因及影響。
四、展延工期。
前項展延以二次為限,展延工期總和不得超過原許可工期之半數。
但因非可歸責於再生水經營業之事由,並經該管主管機關同意者,不在此限。
依促進民間參與公共建設法興辦之再生水開發案,不適用本條規定。
一、基本資料:名稱、負責人、地址、聯絡方式。
二、再生水開發案興建許可及廢(污)水或放流水使用許可影本。
三、展延原因及影響。
四、展延工期。
前項展延以二次為限,展延工期總和不得超過原許可工期之半數。
但因非可歸責於再生水經營業之事由,並經該管主管機關同意者,不在此限。
依促進民間參與公共建設法興辦之再生水開發案,不適用本條規定。