Regulations Governing the Organization of the Selection Committee and the Evaluation for Private Participation in Infrastructure Projects Article 25
The outcome of the comprehensive review shall be reported to the head of the authority in charge or personnel authorized by the head for approval and published on the information network of the competent authority and notification shall be given to each applicant in writing within two weeks of the approval.The outcome of inviting private participation by public notice, including no applicants, no qualified applicants, failure for contract negotiation or execution, or success for contract execution, should be published on the information network of the competent authority.
中文原文 民間參與公共建設甄審委員會組織及評審辦法第25條
綜合評審結果應簽報主辦機關首長或其授權人員核定,並於核定後二週內公開於主管機關資訊網路及以書面通知各申請人。
公告徵求後無申請人、資格審查後無合格申請人、無法完成議約或簽約,或完成簽約者,應公開於主管機關資訊網路。