Regulations for the Review and Approval of Applications for Construction License of Nuclear Source Material and Nuclear Fuel Production and Storage Facilities Article 9

After receipt the documents referred to in Paragraph 1 of Article 3, the competent authority shall complete its review and bulletin the conclusion within the following time limit:1.Nuclear source material storage facilities: six months.2.Nuclear fuel storage facilities: ten months.3.Nuclear source material production facilities: one year.4.Nuclear fuel production facilities: one year and six months.