Regulations for the Review and Approval of Applications for Construction License of Nuclear Source Material and Nuclear Fuel Production and Storage Facilities Article 10
The time limit for reviewing referred to in the preceding Article shall commence from the day when the applicant submits all the necessary documents and pay the licensing fee to the competent authority. The time limit for reviewing referred to in the preceding Paragraph does not include the following periods:1.Not more than sixty days for the related competent authorities to explain the laws or consult with other government agencies (institutions).2.Other delay not attributable to the competent authority.
中文原文 核子原料核子燃料生產貯存設施建造執照申請審核辦法第10條
前條審查期限,自申請者備齊書件,向主管機關繳交審查費之日起算。
前項審查期限,不包括下列期間:
一、相關主管機關釋示法令或會商其他機關(構)未逾六十日之日數。
二、其他不可歸責於主管機關之日數。
前項審查期限,不包括下列期間:
一、相關主管機關釋示法令或會商其他機關(構)未逾六十日之日數。
二、其他不可歸責於主管機關之日數。