The Nuclear Materials and Radioactive Waste Management Act Article 8
For the construction of production (and/)or storage facilities of nuclear source material (and/)or nuclear fuel, an application for construction license shall be filed with the competent authorities, and the construction shall not commence until the application has been reviewed and approved (by the competent authorities) to satisfy the following prescription and the competent authorities have issued a construction license therefor:1.The purpose of construction is consistent with that of peaceful use of atomic energy(; and)2.The equipment and the facilities are sufficient to secure the public health and safety(; and)3.The impact to the environmental ecology complies with the prescription of relevant laws/statutes and decrees(; and)4.The technology, the management ability and the financial basis, etc., of the applicant are competent to operate the facilities.For the construction of production facilities referred to in the preceding Paragraph, the materials to prove the capability of managing, stowing and finally disposing of the radioactive waste to be generated due to the operation thereof shall be submitted (to the competent authorities).The competent authorities shall publicize and display the application referred to in the preceding Paragraph within thirty (30) days of the receipt of it; the time period for publication and display is sixty (60) days. During the time period for publication and display, individuals, government agencies or organizations may submit to the competent authorities reference opinions in written document stating the name or appellation and the address; and a hearing (or hearings) shall be held by the competent authorities subsequently.The regulations for the qualification, documents required, review and approval procedures and other matters to be complied with for an application for construction license for constructing the production (and/)or storage facilities of nuclear source material (and/)or nuclear fuel shall be prescribed by the competent authorities.
中文原文 放射性物料管理法第8條
核子原料、核子燃料生產或貯存設施之興建,應向主管機關提出申請,經審核合於下列規定,發給建造執照後,始得為之:
一、與原子能和平使用之目的一致。
二、設備及設施足以保障公眾之健康及安全。
三、對環境生態之影響合於相關法令規定。
四、申請人之技術與管理能力及財務基礎等足以勝任其設施之經營。
前項生產設施之興建,對運轉所產生之放射性廢棄物,並應檢附資料證明其具有處理、貯存及最終處置能力。
主管機關於收到前項申請後三十日內,應將申請案公告展示;其公告展示期間為六十日。
個人、機關或團體,得於公告展示期間內以書面載明姓名或名稱及地址,向主管機關提出意見;主管機關應舉行聽證。
核子原料、核子燃料生產或貯存設施建造執照申請資格、應備文件、審核程序及其他應遵行事項之辦法,由主管機關定之。
一、與原子能和平使用之目的一致。
二、設備及設施足以保障公眾之健康及安全。
三、對環境生態之影響合於相關法令規定。
四、申請人之技術與管理能力及財務基礎等足以勝任其設施之經營。
前項生產設施之興建,對運轉所產生之放射性廢棄物,並應檢附資料證明其具有處理、貯存及最終處置能力。
主管機關於收到前項申請後三十日內,應將申請案公告展示;其公告展示期間為六十日。
個人、機關或團體,得於公告展示期間內以書面載明姓名或名稱及地址,向主管機關提出意見;主管機關應舉行聽證。
核子原料、核子燃料生產或貯存設施建造執照申請資格、應備文件、審核程序及其他應遵行事項之辦法,由主管機關定之。