Regulations on Relocation Fee of Telecommunications Lines and Bearing Damage Compensation for Telecommunications Equipment Article 15
Those who damage to telecommunications facilities arising from repairs or construction of buildings, roads, irrigation ditches, or the laying of underground pipes, cables or other projects shall take charge of compensation.Construction situations in the proceeding paragraph, besides emergency accident to follow the conduction of other Laws, shall start before 7 days of construction to notify Telecommunications lines authorities in a written notice and carry conduit drawings to the field installation specified by Telecommunications lines. If Telecommunications lines authorities don’t specify on site or specify improperly on site, constructors shall not take liability to pay compensation of damage.
中文原文 電信線路遷移費用及電信設備損壞賠償負擔辦法第15條
因修建房屋、道路、溝渠、埋設管線等工程或其他事故損壞依法設置之電信設備者,應負賠償責任。
前項情形之施工,除緊急事故依其他法令規定辦理者外,應於開始施工七日前,書面通知電信線路所屬機關(構)攜帶管線圖面資料到場指明電信線路設置位置,電信線路所屬機關(構)不到場指明或雖到場指明而指明不正確者,施工者不負損壞賠償責任。
前項情形之施工,除緊急事故依其他法令規定辦理者外,應於開始施工七日前,書面通知電信線路所屬機關(構)攜帶管線圖面資料到場指明電信線路設置位置,電信線路所屬機關(構)不到場指明或雖到場指明而指明不正確者,施工者不負損壞賠償責任。