Upon completion of building telecommunication equipment installation, the building constructor shall submit the following documents to the Inspection Institute for examined design drawing in order to apply for inspection and pay the inspection fee:1. Examination application form according to the rules.2. Building indoor and outdoor telecommunication equipment engineering technique regulation record chart under the construction technique regulation.3. Building telecommunication equipment construction completion checking report of issued architect or professional technician.4. One disc copy containing the electronic files of the contents stated in subparagraph 2, paragraph 4 of the above article. Once inspection documents are fully prepared, the Inspection Institute shall complete inspection within fourteen working days; once inspection is approved, documents submitted for the approval and inspection shall be returned. The constructor or owner can only apply for the certificates below after paying for the approval and submitted certification fees:1. Certificate of cable narrow-band: only telephone main distribution could be installed according to the construction technical regulation.2. Certificate of cable wide-band: telephone and digital distribution may be installed in the building according to the construction technical regulation. The digital backbone and indoor digital distribution adopt unshielded twisted pair, shielded twisted pair or higher level cable design.3. Certificate of Fiber-to-the-Home (FTTH): telephone and digital distribution may be installed in the building under construction technique regulation. The digital backbone adopts the optical fiber cable design, and the indoor digital distribution adopts unshielded twisted pair, shielded twisted pair or higher level cable design.In the case of any of the following circumstances, the Inspection Institute may request building constructor to improve within a certain time period. Failure to amend before the due date or deemed incomplete after amendment have been made within the designated period, the documents shall not be returned.1. Failed to pay inspection fee accordingly2. Failed to submit complete documents3. Incomplete filling of application form contentFor those who are unqualified after inspection, the Inspection Institute shall inform building constructor to make necessary improvements within a certain time period. The document shall not be returned and the application shall be rejected if deemed as failed to make necessary improvements within the designated time period.If rejected according to the aforementioned, the building constructor may re-apply for inspection.The designated time period for item 3 and 4 shall be two months. However, it can be prolonged if needed while the prolonged period may not be longer than two months and only one prolonging period shall be allowed.The building indoor outdoor telecommunication equipment planning/ drawing approval / test examination / inspection operation procedure shall be as Appendix 3. The certificate of building telecommunication equipment shall be as Appendix 4.Appendix III.PDFAppendix III.docAppendix IV.PDFAppendix IV.doc