When designing indoor and outdoor telecommunication equipment and space, the building constructor should prepare “building indoor and outdoor telecommunication equipment planning/ drawing approval / test / examination/ inspection application form” (hereinafter referred to as “Application Form” as shown in Appendix 2) and request the local internet service provider to proceed with pipe input, the installation of telecommunication room, wire box and cable.Accepting the application, the local internet service provider shall complete the entrusted task within 7 working days. Other local internet service providers that did not participate in the operation may not propose objection to the outcome.After received visa according to provision 2 of the previous article, the building telecommunication equipment and related equipment space design drawing shall be examined and inspected by the telecommunications professional institute (hereinafter as “examining institute”) entrusted by this commission before applying for construction. The building constructor shall submit the following documents to the Inspection Institute for examination and and inspection and pay an inspection fee:1. Finished application form according to the rules for applying for planning of the design drawing.2. Building indoor and outdoor telecommunication equipment design checklist and related drawing description (includes floor plan, ascending location chart and building base location chart) under construction technique regulation.In the case of any of the following circumstances, the Inspection Institution shall inform the building constructor to improve within a designated time period. The document shall not be returned if the constructor fails to make the required improvements within the time period.1. Failing to pay the examination fee2. Incomplete examination document3. Incomplete application form contentFor an application with complete examination document, the Inspection Institute shall complete examination within 7 working days. For application disqualified after examination, Inspection Institute shall inform building constructor to improve within a designated time period. The inspection document and fee will not be returned and the application shall be rejected if deemed as failing to amend before the due date or as incomplete after amendments have been made.A rejected application according to previous time, building constructor may re-apply for examination.The designated time period for provision 5 and 6 shall be two months. However, the building constructor’s application may be prolonged if needed. The prolonged time period may not be longer than 2 months and only one prolonging shall be allowed.Appendix II.PDFAppendix II.doc