Soil and Groundwater Pollution Remediation Act Enforcement Rules Article 22

If any of the following items concerning the implementer of a remediation plan approved by a special municipality or county (city) competent authority change, the implementer should apply to make a remediation plan change pursuant to Article 22, Paragraph 4 of this Act, and the change shall be effective after approval by the special municipality or county (city) competent authority:1. Plan submitter information specified in Article 20, Paragraph 1, Subparagraph 1.2. Items specified in Article 20 Paragraph 1, Subparagraphs 5-8, 12, and 14.3. Other matters specified by the special municipality or county (city) competent authority.Any changes apart from those specified in the various subparagraphs of the foregoing paragraph should be reported to the special municipality or county (city) competent authority for subsequent reference.
中文原文 土壤及地下水污染整治法施行細則第22條
經直轄市、縣(市)主管機關核定之整治計畫,其實施者就下列事項變更,應依本法第二十二條第四項規定,提出整治計畫變更之申請,經直轄市、縣(市)主管機關核定後據以實施:
一、第二十條第一項第一款所定計畫提出者之資料。
二、第二十條第一項第五款至第八款、第十二款及第十四款所定事項。
三、其他直轄市、縣(市)主管機關指定之事項。
前項各款所定事項外之變更,應送直轄市、縣(市)主管機關備查。

English translation for reference only; the Chinese text prevails. Not legal advice.