The aviation noise improvement projects for civil airports and civil/military airports under the jurisdiction of civil control towers in Article 15, Paragraph 1 of this Act shall include the following items:I.The operating or management agency (organization) responsible for implementing improvements.II.An explanation of the situation of the noise source and its structure and location (including the complainant's location or measurement point).III.Noise measurement results prior to improvement (including spectrum analysis), analysis of causative factors, and degree of influence.IV.Explanation of the content of the adopted noise control measures. Design illustrations showing the locations, sizes, and functions of relevant noise control facilities shall be included therein.V.Assessment of the improvement function of the adopted noise control measures.VI.Project implementation timetable.VII.Feasibility assessment of improvements.VIII.Other documents designated by the competent authorityThe adopted noise control measures in Subparagraph 4 of the foregoing paragraph shall include the following items:I.The reduction of noise sources and sound levelsII.The reduction of airport noiseIII.Adjustment operating procedures and control trial operation time periods.IV.Dedicated environmental protection personnel.V.The drafting, in consultation with the relevant agencies, of usage strategies for the land surrounding airfieldsVI.Other control measures that are required to be adoptedProcedures for approval of aviation noise improvement projects by special municipality, county, and city competent authorities, deadlines, and implementation methods shall be as prescribed in Article 7, Paragraph 2.If the operating or management agency (organization) fails to complete correction within the time period specified in the foregoing paragraph, the noise improvement project shall be considered not to have been submitted in accordance with Article 29 of this Act.
中文原文 噪音管制法施行細則第9條
本法第十五條第一項之民用機場、民用塔台所轄軍民合用機場航空噪音改善計畫,應包括下列事項:
一、應執行改善之營運或管理機關(構)。
二、噪音發生源狀況說明及其構造、位置(含陳情戶位置或量測點)。
三、改善前噪音量測結果(含頻譜分析)及其成因分析、影響程度。
四、所採取相關噪音防制措施內容說明。
其中有關之噪音防制設施,應記載其位置、規模及功能等設計圖說。
五、採取噪音防制措施之改善功能評估。
六、計畫執行期程。
七、改善可行性分析。
八、其他經主管機關指定之文件。
前項第四款所採取之噪音防制措施,應包括下列事項:
一、減少噪音源及其音量。
二、降低機場噪音。
三、調整操作程序及管制試車時段。
四、應有環保專職人員。
五、協商有關機關擬訂航空站周圍土地之使用對策。
六、其他應採之防制措施。
直轄市、縣(市)主管機關核定航空噪音改善計畫之相關程序、期限及辦理方式依第七條第二項規定辦理。
營運或管理機關(構)逾期未依前項規定完成補正者,視為未依本法第二十九條規定檢送噪音改善計畫。
一、應執行改善之營運或管理機關(構)。
二、噪音發生源狀況說明及其構造、位置(含陳情戶位置或量測點)。
三、改善前噪音量測結果(含頻譜分析)及其成因分析、影響程度。
四、所採取相關噪音防制措施內容說明。
其中有關之噪音防制設施,應記載其位置、規模及功能等設計圖說。
五、採取噪音防制措施之改善功能評估。
六、計畫執行期程。
七、改善可行性分析。
八、其他經主管機關指定之文件。
前項第四款所採取之噪音防制措施,應包括下列事項:
一、減少噪音源及其音量。
二、降低機場噪音。
三、調整操作程序及管制試車時段。
四、應有環保專職人員。
五、協商有關機關擬訂航空站周圍土地之使用對策。
六、其他應採之防制措施。
直轄市、縣(市)主管機關核定航空噪音改善計畫之相關程序、期限及辦理方式依第七條第二項規定辦理。