Stationary Pollution Source Installation, Operating and Fuel Use Permit Management Regulations Amended Clauses Article 20
After public or private premises receive notice for trial operation or air pollutant emission testing from the reviewing agency in accordance with Article 33, they shall follow the procedures below:I.Public or private premises that receive the trial operation notification shall complete trial operation in accordance with the trial operation plan and submit an air pollutant emissions testing report or supporting documents showing compliance with the applicable requirements of this Act to the reviewing agency within 15 days. Those for which testing results demonstrate compliance with emissions standards may continue to perform trial operation.II.Those public or private premises that receive the air pollutant emissions testing notification shall complete testing in accordance with an approved air pollutant emissions testing plan and submit an air pollutant emissions testing report to the reviewing agency within 60 days.The approved trial operation period under Subparagraph I of the previous paragraph shall not exceed 100 days. If the public or private premises are unable to complete trial operation in accordance with the trial operation plan before the approved trial operation deadline, an application for extension may be filed with the reviewing agency before the expiry of the approved trial operation deadline. There shall be no more than 2 applications for extension and the total period of trial operation period, including the originally approved trial operation period, shall not exceed 190 days, unless otherwise approved by the reviewing agency.If an application for extension of trial operation period is filed 15 days before expiry and if the approval or denial of the extension cannot be granted before the expiry of the trial operation period due to the reviewing agency’s review, the public or private premises may continue trial operation in accordance with the trial operation plan during the period after the expiry of the trial operation period until the time when the extension is approved or denied. If the application for extension is not filed 15 days before the expiry of the trial operation period, the public or private premises shall stop trial operation if the reviewing agency does not grant an approval or denial on the extension upon expiry of the trial operation period.If the public or private premises need to revise the trial operation plan during the trial operation period, the amended trial operation plan shall be submitted with the certification by an environmental engineering technician or other relevant professional technician. Following approval by the reviewing agency, trial operation shall be carried out in accordance with the approved contents. Before approval by the reviewing agency, trial operation shall continue based on the contents of the original trial operation plan.
中文原文 固定污染源設置操作及燃料使用許可證管理辦法第20條
公私場所於審核機關依第三十三條通知試車或空氣污染物排放檢測後,應依下列程序辦理:
一、公私場所接到試車通知者,應依試車計畫書完成試車,並於核准試車期限屆滿前十五日內,向審核機關提送空氣污染物排放檢測報告或足供認定符合本法相關規定之證明文件,且其檢測結果符合排放標準者,得繼續進行試車。
二、公私場所應於接到空氣污染物排放檢測通知後六十日內,依核定之空氣污染物排放檢測計畫完成檢測,並向審核機關提送空氣污染物排放檢測報告。
前項第一款之核准試車期限,不得超過一百日。
公私場所無法於核准試車期限內依試車計畫書完成試車者,得於核准試車期限屆滿前向審核機關申請展延,展延申請次數不得超過二次,且含原核准試車期限之試車總日數不得超過一百九十日。
但經審核機關核准者,不在此限。
公私場所於試車期限屆滿十五日前申請展延者,因審核機關審查致試車期限屆滿前無法作成展延之准駁,公私場所得於試車期限屆滿後至試車展延作成准駁期間內,依試車計畫書內容繼續試車;未於試車期限屆滿十五日前申請展延者,審核機關於試車期限屆滿未作成展延之准駁,公私場所應停止試車。
公私場所於試車期間有修正試車計畫書內容之必要者,應檢具修正後經環境工程技師或其他相關專業技師簽證之試車計畫書,經審核機關核准後,依核准內容進行試車。
未經審核機關核准前,得依原試車計畫內容繼續試車。
一、公私場所接到試車通知者,應依試車計畫書完成試車,並於核准試車期限屆滿前十五日內,向審核機關提送空氣污染物排放檢測報告或足供認定符合本法相關規定之證明文件,且其檢測結果符合排放標準者,得繼續進行試車。
二、公私場所應於接到空氣污染物排放檢測通知後六十日內,依核定之空氣污染物排放檢測計畫完成檢測,並向審核機關提送空氣污染物排放檢測報告。
前項第一款之核准試車期限,不得超過一百日。
公私場所無法於核准試車期限內依試車計畫書完成試車者,得於核准試車期限屆滿前向審核機關申請展延,展延申請次數不得超過二次,且含原核准試車期限之試車總日數不得超過一百九十日。
但經審核機關核准者,不在此限。
公私場所於試車期限屆滿十五日前申請展延者,因審核機關審查致試車期限屆滿前無法作成展延之准駁,公私場所得於試車期限屆滿後至試車展延作成准駁期間內,依試車計畫書內容繼續試車;未於試車期限屆滿十五日前申請展延者,審核機關於試車期限屆滿未作成展延之准駁,公私場所應停止試車。
公私場所於試車期間有修正試車計畫書內容之必要者,應檢具修正後經環境工程技師或其他相關專業技師簽證之試車計畫書,經審核機關核准後,依核准內容進行試車。
未經審核機關核准前,得依原試車計畫內容繼續試車。