Regulations for the Management of Setting up Renewable Energy Power Generation Equipment of Power Users above a Certain Contract Capacity Article 7
The compulsory user of renewable energy shall perform the obligation in accordance with Paragraph 1 of the preceding Article. The compulsory installed capacity may be deducted if the following circumstances are met:1. For those who complete the obligations within three years, 20% of the compulsory installed capacity notified by the central competent authority may be deducted.2. For those who complete the obligations within four years, 10% of the compulsory installed capacity notified by the central competent authority may be deducted.If the compulsory user of renewable energy has installed or provided others to setting up renewable energy power generation equipment at the power-use location before the enforcement of the Regulations, the installed capacity of the facility may be deducted from the compulsory installed capacity notified first by the central competent authority, and the limit is 20%.The compulsory user of renewable energy who is applicable to the provisions of the preceding paragraph shall provide the electricity generation license; the self-use power generation equipment registration; or the renewable energy facility registration document, and apply to the central competent authority for approval.
中文原文 一定契約容量以上之電力用戶應設置再生能源發電設備管理辦法第7條
再生能源義務用戶依前條第一項規定履行義務,於符合以下情形者,得扣減其義務裝置容量:
一、於三年內完成義務履行者,扣減中央主管機關通知義務裝置容量之百分之二十。
二、於四年內完成義務履行者,扣減中央主管機關通知義務裝置容量之百分之十。
再生能源義務用戶於本辦法施行日前,已於其用電場所自行或提供他人設置再生能源發電設備者,該設備之裝置容量得扣減中央主管機關第一次通知義務裝置容量,並以百分之二十為限。
再生能源義務用戶適用前項規定者,須檢具發電業執照、自用發電設備登記證或再生能源發電設備登記文件,向中央主管機關申請核可。
一、於三年內完成義務履行者,扣減中央主管機關通知義務裝置容量之百分之二十。
二、於四年內完成義務履行者,扣減中央主管機關通知義務裝置容量之百分之十。
再生能源義務用戶於本辦法施行日前,已於其用電場所自行或提供他人設置再生能源發電設備者,該設備之裝置容量得扣減中央主管機關第一次通知義務裝置容量,並以百分之二十為限。
再生能源義務用戶適用前項規定者,須檢具發電業執照、自用發電設備登記證或再生能源發電設備登記文件,向中央主管機關申請核可。