Regulations on Governing the Establishment Approval for Reclaimed Water Operators and the Approval for Reclaimed Water Development Project Article 16
If the Reclaimed Water Operator applies for approval of change to a reclaimed water construction and operation plan in accordance with Paragraph 5 of Article 9, of the Act, reasons for the change, comparison table for the changed contents, and the relevant certificates and doucumentation shall be submitted to the Competent Authority for approval.Where the change in the preceding Paragraph involves Article 5, Paragraph 2, Subparagraphs 4 to 8 and Subparagraph 10, or is due to the change of name or organization of the Reclaimed Water Operator, the change plan shall be additionally attached to explain the contents of the change and relevant drawings or certifying documents; where it involves Article 5, Paragraph 2, Subparagraphs 5 to 7, it shall be handled in accordance with Articles 9 to 11 and Article 14.