The Electricity Act Article 73

If the Electricity Transmission and Distribution Enterprise is found to engage in any of the below, a fine ranging from NT$2,500,000 to NT$25,000,000 shall be imposed by the Electricity Industry Regulatory Agency and given a time limit to correct the violation. If the Electricity Transmission and Distribution Enterprise fails to take corrective action upon the expiration of the time limit, it shall be fined consecutively:1. Failing to manage electric power dispatching in accordance with paragraph 1, Article 8 of this Act;2. Failing to draft rules governing electric power dispatching in accordance with paragraph 2, Article 8 of this Act; or a significant failure to manage electric power dispatching in accordance with the approved rules.
中文原文 電業法第73條
輸配電業有下列情形之一者,由電業管制機關處新臺幣二百五十萬元以上二千五百萬元以下罰鍰,並得限期改善;屆期未改善者,得按次處罰:
一、未依第八條第一項規定負責執行電力調度。
二、未依第八條第二項規定擬訂電力調度規定,或未依核定之內容執行調度業務,且情節重大。

English translation for reference only; the Chinese text prevails. Not legal advice.