Enforcement Rules of the Government Procurement Act Article 97

Where an entity, pursuant to paragraph 1 of Article 72 of the Act, notifies a contractor to make improvement, remove the rejected item or re-do the work, or replace the rejected item within a time-limit, the entity shall conduct the inspection and acceptance again when the contractor completes the work within the time-limit.The time-limit referred to in the preceding paragraph shall be subject to the decision of the chief inspector if not specified in the contract.
中文原文 政府採購法施行細則第97條
機關依本法第七十二條第一項通知廠商限期改善、拆除、重作或換貨,廠商於期限內完成者,機關應再行辦理驗收。
前項限期,契約未規定者,由主驗人定之。