Act for Promotion of Private Participation in Infrastructure Projects Article 18

Where an infrastructure to be built by a private institution needs to pass through over or under any government- or privately owned land, unless otherwise stipulated by other laws, the private institution hereunder shall negotiate with the relevant authority in charge of the management of the government-owned land or the owner of the private land, as the case may be, for creation of superficies on the needed area. If such an agreement cannot be reached on government-owned land, the private institution may apply to the authority-in-charge, which will forward the application to the Executive Yuan for a final decision, without being subject to the restrictions under Article 25 of the Land Act. If such an agreement cannot be reached on a part of privately owned land, the government may acquire the superficies on such land mutatis mutandis in accordance with the regulations governing expropriation of land, and then lease such land to the private institution for use for favorable rental to be determined mutatis mutandis in accordance with Paragraphs 1 and 2, Article 15.In the event that the land as referred to in the preceding paragraph becomes unsuitable for proper use because it is traversed by routes of the infrastructure project, the land owners may, from the date of the construction until one year after the commencement of the operations of the infrastructure, apply to the authority-in-charge for expropriation of the ownership of such land, and the authority-in-charge shall not reject such application. The compensation for the land so expropriated shall be decided in accordance with Article 16 and shall be given to the relevant owners after deduction of the compensation receivable by the owners for the superficies created. The land costs increased as a result thereof shall be included in the costs of the infrastructure project.The regulations governing the procedures for use of the space over or under the land, the scope of such use, the demarcation of the boundaries, the creation of superficies, the land expropriation, the compensation for expropriation, registration and review of such use as referred to in the preceding two paragraphs shall be prescribed by the central authorities in charge of the relevant industries in conjunction with the Ministry of the Interior.
中文原文 促進民間參與公共建設法第18條
民間機構興建公共建設,需穿越公有、私有土地之上空或地下,除其他法律另有規定外,應與該土地管理機關或所有權人就其需用之空間範圍,協議設定地上權。
其屬公有土地而協議不成時,得由民間機構報請主辦機關核轉行政院核定,不受土地法第二十五條之限制。
其屬私有土地而協議不成時,準用徵收規定取得地上權後,租與民間機構使用,其租金優惠準用第十五條第一項及第二項之規定。
前項土地因公共建設路線之穿越,致不能為相當使用時,土地所有權人得自施工之日起至開始營運後一年內,向主辦機關申請徵收土地所有權,主辦機關不得拒絕;其徵收補償地價,依第十六條規定,並於扣除原設定地上權取得之對價後補償之。
其所增加之土地費用,應計入公共建設成本中。
前二項土地上空或地下使用之程序、使用範圍、界線之劃分及地上權之設定、徵收、補償、登記及審核之辦法,由中央目的事業主管機關會同內政部定之。