Regulations For Private Institution Applying To Participate In The Infrastructure Project Under Its Own Planning Article 16

The competent authority shall, within one year, finish evaluating the application filed by a private institution for participating in the infrastructure project under its own planning. If necessary, the evaluation period may be extended once for a period not exceeding six months; special circumstances may be exempt from this restriction.The evaluation period referred to in the preceding paragraph shall start on the day after the competent authority declares the policy announcement to the day the written notice of the evaluation outcome is given to the applicant. However, where a private institution submits a project outline before the competent authority's policy announcement is made, the evaluation period shall start from the day after the project outline is served on the competent authority.The period referred to in the preceding paragraph does not include the periods given to applicants for submitting omitted information or documents or making corrections or clarifications, or the periods in which private institutions are invited to submit feasibility assessment reports or investment proposals.The special circumstances referred to in Paragraph 1 shall be determined by the authority in charge, which is forbidden to delegate its subordinate entities or to commission other entities (institutions) to conduct such determination.
中文原文 民間自行規劃申請參與公共建設作業辦法第16條
主辦機關審核民間自行規劃申請參與公共建設案件,應於一年內核定,必要時得延長一次,最長不超過六個月。
但情形特殊者,不在此限。
前項審核期間之計算,自主辦機關辦理政策公告之次日起至審核或評審結果以書面通知申請人止。
但民間於主辦機關政策公告前提出規劃構想書者,自規劃構想書送達主辦機關之次日起算。
前項期間,不包含限期申請人補件、補正、提出說明、徵求民間提出可行性評估報告及投資計畫書之期間。
第一項特殊情形應由主辦機關認定,不得授權所屬或委託其他機關(構)辦理。

English translation for reference only; the Chinese text prevails. Not legal advice.