The originator of a place for the manufacture, storage, or handling of public dangerous goods and flammable high-pressure gas as specified in Article 15, Paragraph 1, shall submit the location, construction, and equipment diagrams of the place to the competent authority of the location for review. Only after the review is complete may they report to the competent construction authority for commencement of work.When applying for a use permit for the place specified in the previous paragraph in accordance with the Building Act, the competent construction authority shall inspect its location, construction, and equipment in conjunction with the authority conducting the review in the previous paragraph. Only after they pass the inspection may a use permit be issued.Before the builder of a storage tank for storing liquid public dangerous goods applies for a use permit as stipulated in the previous paragraph, it should be inspected by a professional organization approved by the central competent authority and a certification document of conformity should be issued.The storage tank mentioned in the previous paragraph that reaches a certain scale announced by the central competent authority, the authority holder should commission the professional organization in the previous paragraph to conduct regular inspections, keep records, and keep them for at least five years. Storage tanks set up before the announcement takes effect should complete their first regular inspection within five years from the date the announcement takes effect. The competent authority may send personnel for inspection.The items, methods, qualification standards, frequency of regular inspection, and other matters to be complied with for the inspection of the storage tanks storing liquid public dangerous goods in the previous two paragraphs shall be determined by the central competent authority.The professional organizations specified in the third paragraph, their qualification for application for approval, procedure, required documents, review method, equipment and tools, issuing (replacement) of approval certificates, validity period, changes, revocation, extension, regulations of business operation, establishment, preservation and reporting of data, and other matters to be complied with shall be determined by the central competent authority.The storage tanks of liquid public dangerous goods of a certain scale that should be regularly inspected, if the central competent authority for the business in question has regulations for regular inspections, shall be handled according to its regulations.
中文原文 消防法第15-5條
第十五條第一項所定公共危險物品及可燃性高壓氣體製造、儲存或處理場所之起造人應將該場所之位置、構造及設備圖說,送請場所所在地主管機關審查完成後,始得向主管建築機關申報開工。
前項所定場所依建築法規定申請使用執照時,主管建築機關應會同前項辦理審查之主管機關檢查其位置、構造及設備合格後,始得發給使用執照。
儲存液體公共危險物品之儲槽起造人依前項規定申請使用執照前,應經中央主管機關許可之專業機構完成檢查,並出具合格證明文件。
前項儲槽達中央主管機關公告一定規模者,其管理權人於開始使用後,應委託前項之專業機構實施定期檢查,作成紀錄,並至少保存五年;公告生效前已設置之儲槽,應自公告生效之日起五年內完成初次定期檢查。
主管機關得派員查核。
前二項儲存液體公共危險物品之儲槽檢查項目、方式、合格基準、定期檢查頻率及其他應遵行事項之辦法,由中央主管機關定之。
第三項所定專業機構,其申請許可之資格、程序、應備文件、審核方式、設備器具、許可證書核(換)發、有效期間、變更、廢止、延展、執行業務之規範、資料之建置、保存與申報及其他應遵行事項之辦法,由中央主管機關定之。
第四項達一定規模應實施定期檢查之儲存液體公共危險物品之儲槽,中央目的事業主管機關另有定期檢查規定者,依其規定辦理。