Standards for Establishing Places for Manufacturing, Storing, Processing Public Hazardous Substances and Flammable Pressurized Gases, and Regulations on Safety Control of such Places Article 36

Pipe work for the delivery of the Six Materials at an indoor storage place shall meet the following requirements:1.The pipe work shall be made of steel or metal. However, if it is possible that steel or metal piping causes contamination of operations, double-layered plastic pipe work may be installed;2.The pipe work shall survive 10-min pressure withstanding test without leakage or deformation when applied with a pressure 1.5 times or greater of the maximal normal working pressure. However, if it is difficult to carry out pressure withstanding test using water pressure, it is allowed to carry out the test using air pressure of 1.5 times of the maximal working pressure. For the pipe work that is installed with double-layered plastic piping, the pressure withstanding test is carried out on the inner pipes;3.If the pipe work is provided on the ground, it shall never contact the ground and shall be corrosion proof;4.If the pipe work is buried in the ground, its surface shall be corrosion proof; the joint shall be provided with measures for inspection unless the joint is welded; and5.If heating or refractory equipment is provided, such shall be in construction that is capable of fire prevention.
中文原文 公共危險物品及可燃性高壓氣體製造儲存處理場所設置標準暨安全管理辦法第36條
室內儲槽場所輸送液體六類物品之配管應符合下列規定:
一、應為鋼製或金屬製。
但鋼製或金屬製配管會造成作業污染者,得設置塑材雙套管。
二、應經該配管最大常用壓力之一點五倍以上水壓進行耐壓試驗十分鐘,不得洩漏或變形。
但以水壓進行耐壓試驗確有困難者,得以該配管最大常用壓力之一點一倍以上氣壓進行耐壓試驗。
設置塑材雙套管者,其耐壓試驗以內管為限。
三、設於地上者,不得接觸地面,且外部應有防蝕功能。
四、埋設於地下者,外部應有防蝕功能;接合部分,應有可供檢查之措施。
但以熔接接合者,不在此限。
五、設有加熱或保溫之設備者,應具有預防火災之安全構造。