Regulations on Use Control of Lands and Buildings within New Town Special Areas Before Implementation of Overall Development English Translation Form Article 8

The bases for which construction of temporary buildings is applied for under Article 5 shall be connected to existing laneways that are not narrower than 2m, and the width of conjunction shall be not less than 2m. For the bases that are not connected to existing laneways, paths shall be provided according to the following provisions:1. Where the length is less than 10m, the width shall be 2m or above.2. Where the length is not less than 10m but less than 20m, the width shall be 3m or above.3. Where the length is not less than 20m, the width shall be 5m or above.The site for which construction of temporary factory buildings and facilities is applied for under Article 6 shall be connected to existing laneways that are not narrower than 6m, and the width of conjunction shall be not less than 6m. For the bases that are not connected to existing laneways, paths shall be provided with a width not less than 6m.The length of the paths mentioned in the above paragraphs shall be calculated from the borderline of existing laneway as the starting point, and the lands of paths may not be calculated into the area of building site.
中文原文 新市鎮特定區實施整體開發前區內土地及建築物使用管制辦法第8條
依第五條規定申請臨時建築之基地應與二公尺以上現有巷道相連接,其連接部分之寬度應在二公尺以上。
但未連接現有巷道者,應自設通路,其自設通路規定如下:
一、長度未滿十公尺者,寬度應為二公尺以上。
二、長度十公尺以上未滿二十公尺者,寬度應為三公尺以上。
三、長度二十公尺以上者,寬度應為五公尺以上。
依第六條規定申請臨時建築為廠房設施之基地應與六公尺以上現有巷道相連接,其連接部分之寬度應在六公尺以上。
但未連接現有巷道者,應自設通路,通路之寬度應為六公尺以上。
前二項自設通路長度,應以現有巷道邊界為起點計算,其土地不得計入建築基地面積。

English translation for reference only; the Chinese text prevails. Not legal advice.