Common Duct Act Article 14
The Common Duct system shall be delimited in principle within the right of way. But for engineering necessity it may also over-pass and under-pass the private and public land, or attach to the buildings and structures. However, it shall be undertaken in the place and with the manner of minimal damages, and to compensate with negotiation.While the aforementioned private land can no longer be properly used due to the passing through of Common Duct system, the owner of the land may file a requisition of land from the first day of construction to the end of one (1) year after its completion; the competent authority can not refuse this request. Regarding the aforementioned over-passing and under-passing the land, the review regulations of using procedure, range, boundary delimitation, registration, requisition, compensation shall be prescribed by the central competent authority.
中文原文 共同管道法第14條
共同管道系統以劃設於道路用地範圍為原則,如因工程之必要,得穿越公、私有土地之上空、地下或附著於建築物、工作物。
但應擇其損害最少之處所及方法為之,並以協議方式補償。
前項私有土地因共同管道系統之穿越,致不能為適當使用時,土地所有權人得於施工之日起至完工後一年內請求徵收土地所有權,主管機關不得拒絕。
前二項土地上空或地下之使用程序、使用範圍、界線之劃分、登記、徵收、補償之審核辦法,由中央主管機關定之。
但應擇其損害最少之處所及方法為之,並以協議方式補償。
前項私有土地因共同管道系統之穿越,致不能為適當使用時,土地所有權人得於施工之日起至完工後一年內請求徵收土地所有權,主管機關不得拒絕。
前二項土地上空或地下之使用程序、使用範圍、界線之劃分、登記、徵收、補償之審核辦法,由中央主管機關定之。