Regulations on the Final Disposal of High Level Radioactive Waste and Safety Management of the Facilities Article 6
The operators of disposal facilities shall submit a plan for detailed site investigation, and then start the detailed investigation after the plan is approved by the competent authority.The plan of detailed site investigation referred to in the preceding paragraph shall include the following contents:1. Description of the location.2. Conceptual design of the operating area of disposal facilities.3. Necessity of drilling or excavation and operation planning.4. Research and test plan.5. Plan for investigating and controlling the factors likely to influence the capability of the location to isolate highly radioactive wastes.6. Quality assurance plan.7. Restoration plan.8. Financial description.9. Other contents specified by the competent authority.
中文原文 高放射性廢棄物最終處置及其設施安全管理規則第6條
高放處置設施經營者,應檢附場址詳細調查規劃書,報經主管機關核准後,始得進行場址詳細調查。
前項場址詳細調查規劃書,應載明下列事項:
一、場址區域描述。
二、高放處置設施作業區之概念設計。
三、鑽探或開挖之必要性與作業規劃。
四、研究及測試計畫。
五、可能影響場址隔離高放射性廢棄物能力之調查作業及其管制計畫。
六、品質保證計畫。
七、復原計畫。
八、財務說明。
九、其他經主管機關指定之事項。
前項場址詳細調查規劃書,應載明下列事項:
一、場址區域描述。
二、高放處置設施作業區之概念設計。
三、鑽探或開挖之必要性與作業規劃。
四、研究及測試計畫。
五、可能影響場址隔離高放射性廢棄物能力之調查作業及其管制計畫。
六、品質保證計畫。
七、復原計畫。
八、財務說明。
九、其他經主管機關指定之事項。