Enforcement Rules of the Implementation of Nuclear Reactor Facilities Regulation Act Article 9

A situation arising during the construction period of a nuclear reactor facility that may pose risks to public health, safety, or the ecological environment, as stipulated in Paragraph 1 of Article 14 of this Act, refers to any of the following:1. The design thereof has been found to be in major deficiency but has not yet been appropriately evaluated and solved.2. There is a major discrepancy between the activity of construction and the commitment under the safety analysis report, which might affect the safety function.3. The performance of quality assurance program is seriously deficient, which has caused a gross impact on the quality of construction.4. A serious accident occurs, which adversely affects the construction activities.5. After evaluation, the estimated radiation dose to the general public by the prospectively completed nuclear reactor facility might exceed the dose limit prescribed under the Safety Standards for Protection against Ionizing Radiation.6. The submitted documents, materials or records are false, which has affected the accuracy of reviewing or issuing the license by the competent authority.7. After evaluation, the prospectively completed nuclear reactor facility might not comply with the prescriptions provided under respective subparagraphs of Paragraph 1 of Article 5 of this Act8. Other circumstances determined and published by the competent authority.
中文原文 核子反應器設施管制法施行細則第9條
本法第十四條第一項所稱核子反應器設施興建期間,有危害公眾健康與安全或環境生態之虞者,指有下列情事之一:
一、發現設計有重大缺陷,且未經適當評估解決。
二、興建施工作業與安全分析報告承諾有重大差異,且影響安全功能。
三、品質保證方案之執行有嚴重缺陷,對工程品質產生重大影響。
四、發生重大意外事件,對興建施工作業有不良影響。
五、經評估未來興建完成之核子反應器設施,對一般人造成之劑量超過游離輻射防護安全標準規定之劑量限度。
六、提供不實之文件、資料或紀錄,致影響主管機關審核或核發執照之正確性。
七、經評估未來興建完成之核子反應器設施,無法符合本法第五條第一項各款規定。
八、其他經主管機關認定並發布之情事。