Regulations on the Permit Application and the Management for Decommissioning of Nuclear Reactor Facilities Article 6
The review period referred to in the preceding Article shall commence from the day when the applicant has prepared all the required documents.The review period referred to in the preceding paragraph does not include the following periods:(1) Not exceeding sixty days for the relevant competent authority to interpret the laws or consult with other government agencies (institutions).(2) Other delays not attributable to the competent authority.
中文原文 核子反應器設施除役許可申請審核及管理辦法第6條
前條審查期限,自經營者備齊書件之日起算。
前項審查期限,不包括下列期間:
一、相關機關釋示法令或會商其他機關(構)未逾六十日之日數。
二、其他不可歸責於主管機關之日數。
前項審查期限,不包括下列期間:
一、相關機關釋示法令或會商其他機關(構)未逾六十日之日數。
二、其他不可歸責於主管機關之日數。