Regulations on the Permit Application and the Management for Decommissioning of Nuclear Reactor Facilities Article 12

The licensee shall submit an annual implementation report and a revised version of the decommissioning plan in accordance with approved decommissioning plan to the competent authority for review and approval by March 31 each year.Annual implementation report under the preceding paragraph shall include the following contents:(1) The completed tasks of decommissioning, ongoing tasks, and the expenditures of the previous year.(2) The important tasks and estimated expenditures which are planned to be executed for the current year.(3) Analysis of integrated activities of decommissioning, accumulated expenditures, and the latest cost estimation of integrated expenditures of decommissioning.
中文原文 核子反應器設施除役許可申請審核及管理辦法第12條
經營者應於每年三月三十一日前,依核定之除役計畫,提出年度執行報告及除役計畫修正版,報請主管機關審核。
前項年度執行報告,應包括下列事項:
一、前一年度除役作業執行完成事項、持續進行事項及經費使用情形。
二、本年度規劃執行除役作業重要工作事項及經費使用預估。
三、除役作業整體進度評估、累計經費使用情形及最新除役整體經費概算。

English translation for reference only; the Chinese text prevails. Not legal advice.