Regulations on Treatment and Storage of Radioactive Waste and Safety Management of the Facilities Article 18
Where corrosion or deformation of containers or deterioration of the solidified waste is found in the evaluation of the storage facilities performed once every ten years, the operator shall submit a maintenance plan including the following contents to the competent authority, and implement the plan after it is approved:1.General descriptions of the operation, including work contents, personnel organization, time schedule, work place, and layout of the storage area after maintenance is finished.2.Equipment used for maintenance, including treatment equipments and solidifying agents.3.Procedure of maintenance.4.Radiation protection measures.5.Waste management after maintenance is finished.6.Industrial safety and hygiene measures.7.Evaluation for personnel dose and environmental radiation impacts.8.Response measures for accidents.9.Quality assurance measures.10.Other matters designated by the competent authority.The operators shall, within six months after the maintenance plan is finished, submit a report on the process of maintenance to the competent authority for review and approval.
中文原文 放射性廢棄物處理貯存及其設施安全管理規則第18條
貯存設施經十年再評估後,發現盛裝容器銹蝕、變形或固化體劣化時,經營者應提出載明下列事項之檢整計畫,報請主管機關核准後實施檢整作業:
一、作業概述,含工作內容、人員編組、工作時程表、作業場所及檢整後之貯存區佈置等。
二、檢整作業相關設備,含處理設備或固化劑等。
三、檢整作業程序。
四、輻射防護措施。
五、檢整作業後之廢棄物處理。
六、工業安全衛生措施。
七、人員劑量及環境輻射影響評估。
八、意外事故之應變措施。
九、品質保證措施。
十、其他經主管機關指定之事項。
檢整計畫執行完成後六個月內,經營者應就檢整作業經過提出報告,報請主管機關備查。
一、作業概述,含工作內容、人員編組、工作時程表、作業場所及檢整後之貯存區佈置等。
二、檢整作業相關設備,含處理設備或固化劑等。
三、檢整作業程序。
四、輻射防護措施。
五、檢整作業後之廢棄物處理。
六、工業安全衛生措施。
七、人員劑量及環境輻射影響評估。
八、意外事故之應變措施。
九、品質保證措施。
十、其他經主管機關指定之事項。
檢整計畫執行完成後六個月內,經營者應就檢整作業經過提出報告,報請主管機關備查。