Enforcement Rules of the Nuclear Materials and Radioactive Waste Management Act Article 26
Before to apply for operating license of radioactive waste treatment, storage or final disposal facilities according to Paragraph 1 of Article 18 of this Act, the applicant shall submit trial operation plan to the competent authority to apply for trial operation at first.After trial operation is finished in accordance with the above paragraph, a letter of application enclosed with the following documents shall be submitted to the competent authority to apply for operation license:1.Safety analysis report of the latest edition.2.Facility operating technical specifications.3.Trial operation report.4.Accident response plan.5.Other documents designated by the competent authority.The time limits for the competent authority to examine the above-mentioned applications are as follows:1.Examination of application for radioactive waste treatment or storage facilities shall be finished within 3 months.2.Examination of applications for low-activity waste final disposal facilities shall be finished within 6 months.3.Examination of applications for high-activity waste final disposal facilities shall be finished within 1 year.
中文原文 放射性物料管理法施行細則第26條
依本法第十八條第一項規定申請放射性廢棄物處理、貯存或最終處置設施運轉執照者,應先檢附試運轉計畫,報經主管機關核准進行試運轉。
依前項規定完成試運轉後,應填具申請書,並檢附下列資料,向主管機關申請核發運轉執照:
一、最新版之安全分析報告。
二、設施運轉技術規範。
三、試運轉報告。
四、意外事件應變計畫。
五、其他經主管機關指定之資料。
主管機關對於前項申請案之審查,其處理期間如下:
一、申請放射性廢棄物處理或貯存設施者,三個月。
二、申請低放射性廢棄物最終處置設施者,六個月。
三、申請高放射性廢棄物最終處置設施者,一年。
依前項規定完成試運轉後,應填具申請書,並檢附下列資料,向主管機關申請核發運轉執照:
一、最新版之安全分析報告。
二、設施運轉技術規範。
三、試運轉報告。
四、意外事件應變計畫。
五、其他經主管機關指定之資料。
主管機關對於前項申請案之審查,其處理期間如下:
一、申請放射性廢棄物處理或貯存設施者,三個月。
二、申請低放射性廢棄物最終處置設施者,六個月。
三、申請高放射性廢棄物最終處置設施者,一年。