For the permanent cease of operation of production (and/)or storage facilities of nuclear source material (and/)or nuclear fuel, the operator shall prepare a decommission plan and shall implement it after the same has been reported to and approved by the competent authorities; and during the implementation period, the competent authorities may dispatch the inspector(s) to inspect the same at anytime; and after the completion of decommission, the operator shall report it to the competent authorities for inspection.Where the facilities referred to in the preceding Paragraph have ceased operating for more than one (1) year consecutively but the operator does not report it to the competent authorities for approval, it shall be deemed as the permanent cease of operation; and the decommission procedure shall follow the prescription of the preceding Paragraph.The decommission referred to in Paragraph 1 shall be completed within fifteen (15) years of the permanent cease of operation.
中文原文 放射性物料管理法第14條
核子原料、核子燃料生產或貯存設施永久停止運轉,其經營者應擬訂除役計畫,報請主管機關核准後實施;實施期間,主管機關得隨時派員檢查;除役完成後,經營者應報請主管機關檢查。
前項設施之停止運轉,未經報請主管機關核准,持續達一年以上者,視為永久停止運轉;其除役程序,依前項之規定。
第一項之除役,應於永久停止運轉後十五年內完成。
前項設施之停止運轉,未經報請主管機關核准,持續達一年以上者,視為永久停止運轉;其除役程序,依前項之規定。
第一項之除役,應於永久停止運轉後十五年內完成。