Regulations Governing Interconnection involving Significant Market Power Article 7

When a significant market power offers network interconnection service, the point of interconnection shall be set up at any places that are technically feasible.When the technical feasibility evaluation indicates inability to set up points of network interconnection, the significant market power shall explain the reason to the party that requests the interconnection in written form, and provide the information of other alternative interconnection points.The following interconnection points are technically feasible:1. Local switches.2. Local tandem switches.3. Toll switches.4. International switches.5. Dedicated tandem switches.6. Signal transfer points.7. Cross-connection points.8. Other precedents of points of interconnection.The following principles shall be adhere to when evaluating the technical feasibility:1. Whether the network interconnection affects the security or reliability of telecommunications networks.2. Space, location and economic factors are prohibited from being reasons for technical unfeasibility.A significant market power may set up interconnection points beyond the technically feasible points set forth in Paragraph 3 as required by other telecommunications enterprises and shall charge cost-oriented rates.
中文原文 市場顯著地位者互連管理辦法第7條
市場顯著地位者提供互連時,應於任一技術可行點設置網路介接點。
市場顯著地位者經評估技術可行性,遇有無法設置網路介接點之情事,應以書面向提出互連要求之一方說明理由,並另提供其他替代網路介接點之資訊。
下列網路介接點為技術可行點:
一、市內交換機。
二、市內彙接交換機。
三、長途交換機。
四、國際交換機。
五、專用彙接交換機。
六、信號轉送點。
七、交換中心之交接點八、其他已有前例之網路介接點。
評估技術可行性,應遵循下列原則:
一、應考慮互連有無損害電信網路安全性或可靠性之虞。
二、不得以空間、場所及經濟性因素作為技術不可行之理由。
市場顯著地位者得依其他電信事業之要求,於第三項所列技術可行點以外設置網路介接點,並應按成本計價。