Soil and Groundwater Pollution Remediation Act Article 19
(a) Those persons engaging in the excavation, backfill, temporary storage, and transport of soil or groundwater extraction within a pollution control zone shall submit a cleanup or pollution prevention plan to the special municipality, county, or city competent authority, and may implement work only after obtaining approval thereof.(b) If the work in the preceding paragraph is to be performed by the special municipality, county, or city competent authority, the work may be implemented only after reporting to the central competent authority and receiving approval thereof.(c) The special municipality, county, or city competent authority, or central competent authority, shall complete review within three months after submission of the cleanup or pollution prevention plan in the two preceding paragraphs.(d) The cleanup or pollution prevention plan in paragraph 1 may be submitted as part of a pollution control plan, pollution remediation plan, or other pollution improvement plan.
中文原文 土壤及地下水污染整治法第19條
於土壤、地下水污染管制區內從事土壤挖除、回填、暫存、運輸或地下水抽出等工作者,應檢具清理或污染防治計畫書,報請直轄市、縣(市)主管機關核定後,始得實施。
前項工作,由直轄市、縣(市)主管機關為之者,應報請中央主管機關核定後,始得實施。
直轄市、縣(市)或中央主管機關應於前二項清理或污染防治計畫書提出後三個月內,完成審核。
第一項清理或污染防治計畫書,得合併於污染控制計畫、污染整治計畫或其他污染改善計畫中提出。
前項工作,由直轄市、縣(市)主管機關為之者,應報請中央主管機關核定後,始得實施。
直轄市、縣(市)或中央主管機關應於前二項清理或污染防治計畫書提出後三個月內,完成審核。
第一項清理或污染防治計畫書,得合併於污染控制計畫、污染整治計畫或其他污染改善計畫中提出。