Environmental Impact Assessment Enforcement Rules Article 16

Those special circumstances referred to in the proviso in Article 7, Paragraph 2 of this Act and in the proviso in Article 13, Paragraph 3 of this Act means those development activities for which one of the following circumstances apply.I. Those development activities of a massive scale, with an extensive area of impact and for which a review cannot be completed within a short periodII. Those development activities that are highly controversial and for which a review cannot be completed within a short period.
中文原文 環境影響評估法施行細則第16條
本法第七條第二項但書及第十三條第三項但書所稱情形特殊者,指開發行為具有下列情形之一者:
一、開發行為規模龐大,影響層面廣泛,非短時間所能完成審查者。
二、開發行為爭議性高,非短時間所能完成審查者。

English translation for reference only; the Chinese text prevails. Not legal advice.