Environmental Impact Assessment Act Article 14

The industry competent authority may not grant permission for a development activity prior to the completion of an environmental impact statement review or the authorization of an environmental impact assessment report; permission granted in violation of this regulation shall be invalid.The industry competent authority may not grant permission for development activity to those developers that the competent authority determines through review shall not be granted permission to implement development activities. However, the developer may submit an alternate plan to the competent authority for a new review.The alternative plan submitted by the developer pursuant to the preceding paragraph may not conflict with the original reason the competent authority determined that permission shall not be granted if the development activity is replanned based on the original location.
中文原文 環境影響評估法第14條
目的事業主管機關於環境影響說明書未經完成審查或評估書未經認可前,不得為開發行為之許可,其經許可者,無效。
經主管機關審查認定不應開發者,目的事業主管機關不得為開發行為之許可。
但開發單位得另行提出替代方案,重新送主管機關審查。
開發單位依前項提出之替代方案,如就原地點重新規劃時,不得與主管機關原審查認定不應開發之理由牴觸。

English translation for reference only; the Chinese text prevails. Not legal advice.