Water Pollution Control Measures and Test Reporting Management Regulations Article 59
In the event that an enterprise or sewage system utilizes wastewater or sewage treatment/pre-treatment facilities, a functional test shall be conducted within the time frame specified by the competent authority if at least one of the following circumstances applies:I. The circumstances described in Article 56, Paragraph 1, Subparagraph 1.II. Abnormal operating parameters.III. Abnormalities in the equilibrium of water quality or flow.IV. Dilution may have been performed without a permit.V. The functions of the wastewater or sewage treatment/pretreatment facilities may be insufficient.Upon completion of the functional test in the preceding paragraph, the enterprise or sewage system shall submit a functional test report. Alteration of the documents of approval or permits (documents) for water pollution control measure plans shall be in accordance with applicable regulations. In the event a functional test report requires the signature of a technician, the report shall be signed by the technician who has jointly participated in the test.If the result of a functional test indicates nonconformity of the water quality to the control standards specified in the Act, the enterprise or sewage system shall reduce or terminate its production or service, or take other response measures.
中文原文 水污染防治措施及檢測申報管理辦法第59條
事業或污水下水道系統採廢(污)水(前)處理設施且有下列情形之一者,應依主管機關規定期限,進行功能測試:
一、第五十六條第一項第一款。
二、操作參數異常。
三、水質水量平衡異常。
四、有未經許可稀釋之虞。
五、廢(污)水(前)處理設施有功能不足之虞。
前項功能測試完成後,事業或污水下水道系統應提報功能測試報告;涉及水措計畫核准文件或許可證(文件)之變更者,應依規定辦理變更;應經技師簽證者,該功能測試報告應由共同參與功能測試之技師簽證。
事業或污水下水道系統功能測試結果,其水質未符合本法所定管制標準者,應採行減少、停止生產、服務或其他應變措施。
一、第五十六條第一項第一款。
二、操作參數異常。
三、水質水量平衡異常。
四、有未經許可稀釋之虞。
五、廢(污)水(前)處理設施有功能不足之虞。
前項功能測試完成後,事業或污水下水道系統應提報功能測試報告;涉及水措計畫核准文件或許可證(文件)之變更者,應依規定辦理變更;應經技師簽證者,該功能測試報告應由共同參與功能測試之技師簽證。
事業或污水下水道系統功能測試結果,其水質未符合本法所定管制標準者,應採行減少、停止生產、服務或其他應變措施。