Management Regulations for Construction Project Air Pollution Control Facilities Article 16
During construction project periods, construction project owners shall keep sprinkling with water to maintain moisture when engaging in any excavation, reclamation, transportation loading/unloading, compaction or screening work that generates fugitive dust emissions, or any operation that may easily cause fugitive dust emissions.The requirements referred to in the foregoing paragraph shall not apply to construction projects within areas where stage-3 and stage-4 policies to stop and restrict water supply are implemented, upon authorization of the Ministry of Economic Affairs.
中文原文 營建工程空氣污染防制設施管理辦法第16條
營建業主於營建工程進行期間,從事具粉塵逸散性之開挖、回填、搬運、裝卸、夯實、篩分或其他易致粉塵逸散之作業前,應灑水保持濕潤。
前項規定,於經濟部核定第三及第四階段停止及限制供水措施區域內之營建工程,不適用之。