Management Regulations for Construction Project Air Pollution Control Facilities Article 14
During demolition work for construction projects, construction project owners shall use one of the following control measures to effectively suppress fugitive dust emissions:I. Installing pressurized water spraying facilities and keeping them spraying water during the demolition workII. Draping dust-control fabric around building structuresIII. Installing blocking facilities at the height of 2.4 meters around the structuresConstruction projects in the foregoing paragraph that are Type 1 projects shall concurrently employ at least the control measures in subparagraphs 1 and 2.
中文原文 營建工程空氣污染防制設施管理辦法第14條
營建業主於營建工程進行拆除期間,應採行下列有效抑制粉塵之防制設施之一:
一、設置加壓噴水設施,並於拆除作業期間持續噴水。
二、於結構體包覆防塵布。
三、於結構體四周設置高度達二.四公尺之阻隔設施。
前項屬第一級營建工程者,應至少同時採行第一款、第二款之防制設施。
一、設置加壓噴水設施,並於拆除作業期間持續噴水。
二、於結構體包覆防塵布。
三、於結構體四周設置高度達二.四公尺之阻隔設施。
前項屬第一級營建工程者,應至少同時採行第一款、第二款之防制設施。