Waste Incinerator Dioxin Control and Emission Standards Article 10

Incinerators already constructed or that are in the process of being constructed, for which project tender procedures have been completed, or if no tenders were invited, for which project contracts were issued and signed before August 8, 1999, and for which dioxin emission standards were not listed in the project tender criteria and have documentary proof for this, shall comply with dioxin emission standard values from August 8, 2001.
中文原文 廢棄物焚化爐戴奧辛管制及排放標準第10條
八十六年八月八日以前已完成建造、建造中、完成工程招標程序或未經招標程序已完成工程發包之簽約,並未將戴奧辛排放標準列於工程招標規範,且具相關證明文件之焚化爐,應自九十年八月八日起符合奧辛排放標準值。

English translation for reference only; the Chinese text prevails. Not legal advice.