Stationary Pollution Source Installation, Operating and Fuel Use Permit Management Regulations Amended Clauses Article 13

The contents of the air pollution control plan referred to in the 1st paragraph of the previous Article shall include the following items:I.Plan objectives.II.A diagram of the environment within the two kilometers surrounding the pollution source plant.III.A layout diagram of plant facilities.IV.Flowcharts of production and manufacturing processes and production and manufacturing schedules.V.Types, compositions and usage quantities of raw materials and fuel connected with air pollutant emissions, and types and output volumes of products.VI.Conveyance, storage and piling methods for raw materials and components and fuel connected with air pollutant emissions.VII.Types, compositions and concentrations of emitted air pollutants.VIII.Estimated annual quantity of emissions of sulfur oxides, nitrogen oxides, particulate matters and volatile organic compounds subject to approval.IX.Types, structure, performance, processes, usage conditions and design drawings of air pollution collection and emission pipe facilities, monitoring facilities and control facilities or meters.X.Budget for and progress of the installation of air pollution collection and emissions pipe facilities and control facilities.XI.Pollution control facilities adopted by the public or private premises during the installation and construction period.XII.Other items designated by the competent authority.
中文原文 固定污染源設置操作及燃料使用許可證管理辦法第13條
前條第一項所稱之空氣污染防制計畫,其內容應包括下列事項:
一、計畫目標。
二、污染源廠場周界外二公里範圍內之環境座落圖說。
三、廠場設施平面配置圖說。
四、生產製程流程圖說及產製期程。
五、與空氣污染物排放有關之原(物)料、燃料之種類、成分及用量,產品種類及生產量。
六、與空氣污染物排放有關之原(物)料、燃料之輸送、貯存及堆置方式。
七、排放空氣污染物之種類、成分及濃度。
八、預估需核定之硫氧化物、氮氧化物、粒狀污染物及揮發性有機物之年排放量。
九、空氣污染收集及排放管道設施、監測設施、防制設施或儀表之種類、構造、效能、流程、使用狀況及其設計圖說。
十、空氣污染收集及排放管道設施、防制設施之設置經費及進度。
十一、公私場所設立施工期間採取之污染防制設施。
十二、其他經中央主管機關指定之事項。