Regulations for the Management of Tourist Amusement Enterprise Article 15-1

In any of the situations listed below, the approval of a tourist amusement enterprise business plan and the enterprise's original establishment approval shall be rendered null and void:1. Where construction has not been carried out in accordance with the approved plan, and the competent authority having set a time limit of one year for submission of an application to change the business plan, no such application or request for extension has been submitted within the time limit, or the application has been rejected by the competent authority. A request for extension of the time limit shall state the reason why the application cannot be made within the time limit. such extension may not exceed one year at a time, and may be granted no more than two times.2. The development permit issued by the local land administration authority is invalid.3. Failure to complete the development and obtain a tourist amusement enterprise license within the development timeframe of the business plan as approved.In a situation as stipulated in Subparagraph 1 of the preceding paragraph, where the change involves expansion of the area for which the application for establishment was made, only the approval for such changed part of the business plan shall be rendered null and void.
中文原文 觀光遊樂業管理規則第15-1條
觀光遊樂業興辦事業計畫之核定及其原籌設之核准,有下列情事之一者,失其效力:
一、未依核定計畫興建,經主管機關限期一年內提出申請變更興辦事業計畫,屆期未提出申請變更、延展或申請案經主管機關駁回;其申請延展,應敘明未能於期限內申請之理由,延展之期間每次不得超過一年,並以二次為限。
二、土地主管機關核發之開發許可失效。
三、未於核定之興辦事業計畫開發期程內完成開發並取得觀光遊樂業執照者。
前項第一款規定情形,屬申請籌設面積範圍擴大之變更者,僅就該興辦事業計畫核定變更部分,失其效力。

English translation for reference only; the Chinese text prevails. Not legal advice.