Regulations Governing Airport Terminal Preparation, Construction, and Operation Article 7
The construction plan shall include the following:1) Plan objectives and target year.2) Air traffic volume analysis and forecast.3) Terminal planning.4) Air traffic service planning.5) Planning for areas where construction is prohibited or restricted.6) Impact Analysis of peripheral obstacles and removal plan.7) Current status of peripheral land and future development plan.8) Land acquisition approaches.9) Planning for access roads.10) Financial Plan.11) Economic benefit analysis.12) An environmental impact report or environmental impact assessment as reviewed and approved by the competent authorities if, according to relevant laws and/or regulations, an environmental impact assessment shall be conducted.13) Other matters in relation to construction planning.
中文原文 航空站籌設興建及營運管理辦法第7條
興建規劃書應包括下列事項:
一、規劃目的及規劃目標年。
二、航空運量分析及預測。
三、場站規劃。
四、飛航服務規劃。
五、禁限建範圍規劃。
六、周邊障礙物之影響分析及排除計畫。
七、周邊土地現況及未來發展計畫。
八、土地取得方式。
九、聯外道路規劃。
十、財務計畫。
十一、經濟效益評估。
十二、依法令規定應辦理環境影響評估者,應檢附環境影響評估法主管機關審查通過之環境影響說明書或環境影響評估報告書及其核定函影本。
十三、其他與興建規劃有關事項。
一、規劃目的及規劃目標年。
二、航空運量分析及預測。
三、場站規劃。
四、飛航服務規劃。
五、禁限建範圍規劃。
六、周邊障礙物之影響分析及排除計畫。
七、周邊土地現況及未來發展計畫。
八、土地取得方式。
九、聯外道路規劃。
十、財務計畫。
十一、經濟效益評估。
十二、依法令規定應辦理環境影響評估者,應檢附環境影響評估法主管機關審查通過之環境影響說明書或環境影響評估報告書及其核定函影本。