Railway construction shall commence and end within the deadlines ratified by the MOTC. If construction cannot commence or be completed within the deadlines, an application to the MOTC is required in order to ratify postponements of the said deadlines.Upon completion of all or part of a railway construction, the proper authority shall report to the MOTC to execute the MOTC test and be ratified before being put into operation.