Regulations on Rewarding for Demonstration of Renewable Energy Installation in Indigenous Areas Article 11

The processing period for the planning and assessment stage shall be limited to one year from the date of approval of the reward by the Ministry. Nevertheless, if completion as scheduled is not possible due to force majeure, the reward recipient may apply to the Ministry for a six-month extension before the deadline, and such extension shall be limited to one time only.The processing period for the implementation and installation stage shall be limited to one year from the date of approval of the reward by the Ministry. Nevertheless, if installation cannot be completed as scheduled due to force majeure, the reward recipient may apply to the Ministry for a six-month extension before the deadline, and such extension shall be limited to two times only.The reward recipient shall, within the processing period specified in the preceding paragraph, execute an agreement with the installer of the renewable energy power generation equipment and submit it to the Ministry for recordation.The agreement referred to in the preceding paragraph shall specify the installation schedule, the obligations to be performed by the installer of the renewable energy power generation equipment, and the relevant provisions for the Ministry to dispatch personnel for inspection.
中文原文 原住民地區參與再生能源設置示範獎勵辦法第11條
規劃評估階段之辦理期程,自本部獎勵核定之日起一年為限。
惟因不可抗力事由致無法如期完成,受獎勵對象得於期限屆滿前向本部申請展延半年,並以一次為限。
執行設置階段之辦理期程,自本部獎勵核定之日起一年為限。
惟因不可抗力事由致無法如期完成設置,受獎勵對象得於期限屆滿前向本部申請展延半年,並以二次為限。
受獎勵對象應於前項辦理期程內,與再生能源發電設備設置者簽訂契約書,並送本部備查。
前項契約書應載明設置期程、再生能源發電設備設置者需履行之義務及本部得派員查核等相關規定。

English translation for reference only; the Chinese text prevails. Not legal advice.