Regulations on Governing the Establishment Approval for Reclaimed Water Operators and the Approval for Reclaimed Water Development Project Article 7

The Competent Authority shall, in order to review applications stipulated in Paragraph 1 of Article 4, be joined by the central competent authority and the central competent authority for sewer systems, and may invite representatives of relevant authorities, experts and scholars to form review meetings to conduct the review. When necessary, the applicant may be notified to attend and provide explanation.When reviewing a phase one application in Article 4, Paragraph 1, Subparagraph 1, the Competent Authority shall complete such within three months after the announcement period expires; when necessary, review may be extended once for a maximum of three months, and the applicant shall be notified of the review result.When reviewing a phase two application in Article 4, Paragraph 1, Subparagraph 2, the Competent Authority shall complete the review within six months from the date of receiving the reclaimed water construction and operation plan; when necessary, review may be extended once for a maximum of six months.
中文原文 再生水經營業籌設許可及再生水開發案興辦許可辦法第7條
該管主管機關為審查第四條第一項規定申請,應會同中央主管機關及中央下水道主管機關,並得邀集相關機關代表、專家、學者組成審查會為之,必要時得通知申請人列席說明。
該管主管機關審查第四條第一項第一款規定之第一階段申請,應於公告期間屆滿後三個月內完成,必要時得延長一次,以三個月為限,並將審查結果通知申請人。
該管主管機關審查第四條第一項第二款規定之第二階段申請,應於收受再生水興建及營運計畫書之日起六個月內完成審查,必要時得延長一次,以六個月為限。

English translation for reference only; the Chinese text prevails. Not legal advice.